The Town annually and proactively replaces water mains whose age and condition make them vulnerable to unexpected service interruptions and costly repairs. The 2019 water main replacement project locations are shown in the map below and listed beneath. The water mains on these streets will be upgraded to ductile iron pipe designed to the current Town of Cary standards in order to continue providing high-quality water service to these areas. Select an area of the map for more details.

 

This project involves replacing the water main along a portion of Walker Street (Chatham Street to Byrum Street), a portion of Byrum Street (Walker Street to Walnut Street), a portion of Madison Avenue (Beech Street to Crest Road), Crest Road, a portion of Ralph Drive (Carolyn Court to E Cornwall Road), a portion of E Cornwall Road (Washington Street to Cindy Street), Cindy Street and a portion of the Walnut Hills subdivision which includes Sturdivant Drive (Lane Drive to Manchester Drive), Wickham Drive, Manchester Drive (Wickham Drive to Sturdivant Drive), and Askham Drive (from Sturdivant Drive to Manchester Drive).

Project Award: The Project has been awarded to Garney Companies, Inc.

Schedule: Construction for the project is anticipated to begin in March 2019 and anticipated to be complete by spring 2020.  While the contractor may schedule work on one segment at a time, there is possibility of adding crews to work in more than one area simultaneously as needed.