Construction Update - June 2020

Project is 90% complete. On June 4th, both intersection plans were fully implemented. This means new crosswalks with pedestrian signals at both locations. At New Waverly Place, flashing yellow arrows were added and placed in operation. Cary's Signal group is scheduling a final inspection to address any outstanding issues.

Project Background

Town Council authorized staff to design and upgrade the traffic signal located at Tryon Road and New Waverly Place. Design includes new crosswalks on all approaches, new pedestrian signal heads and flashing yellow arrow signals on Tryon Road. The Capital Project fund is ST 1247. The estimated construction cost for the traffic signal is $200,000.