What's Happening Now

September 7, 2018

Work has begun on Chapel Hill Road with the section between NW Maynard Road and Linda Drive complete.  

August 24, 2018

Resurfacing is expected to be completed from Gregory Drive and Harrison Avenue this week before beginning work to the west of Harrison Avenue.

August 17, 2018

Crews continue weather-dependent work between Gregory Drive and Harrison Avenue.

August 10, 2018

This week, the remaining lanes between East Chatham Street and Gregory Drive will be paved before work moves to the section between Gregory Drive and Harrison Avenue. 

July 27, 2018

Paving from Kildaire Farm Road to Walnut Street is almost complete.  Work will pick up north of the railroad tracks at East Chatham Street to avoid ongoing water locating and marking.

July 20, 2018

NCDOT is working to complete paving along SW Maynard Road from Pond Drive to Kildaire Farm Road before beginning the section from Kildaire Farm to Walnut Street next week.

July 13, 2018

Paving along SW Maynard Road from High House Road to Castalia Drive is complete. Next week, NCDOT anticipates completing work between Castalia Drive and Pond Drive and beginning work from Pond Drive to Kildaire Farm Road. 

July 2, 2018

Contractors working for the North Carolina Department of Transportation are scheduled to start daytime utility adjustments along Maynard Road between High House Road and Old Apex Road on July 5, 2018. Repaving along this section of Maynard Road is scheduled to start on or after the evening of July 8, 2018. Lane closures will be necessary to complete this work.

Project Summary

The N.C. Department of Transportation plans to resurface most of Maynard Road from N.C. 54/Chapel Hill Road clockwise to High House Road, starting in July. The NCDOT also plans to resurface Chapel Hill Road between NW Maynard Road and Linda Drive and between Weston Parkway and Perimeter Park Drive, as well as Louis Stephens Drive between Morrisville Carpenter Road and McCrimmon Parkway. 

A contractor working on behalf of NCDOT will conduct repaving work nights between 7 p.m. and 6 a.m. Monday through Friday and weekends through winter with occasional weekday utility work. No work will be conducted during peak travel times. NCDOT work is exempt from the Town's noise ordinance. 

Questions and comments should be directed to NCDOT at (919) 835-8211. For detours and updates, follow the Town of Cary on Twitter @TOC_Traffic, NCDOT on Twitter, @NCDOT_Triangle, and navigate via the Waze app on your smartphone.