Live Traffic Map

  

What's Happening Now

Construction Update - July 14, 2018

Grading has begun on southbound Cary Parkway and is expected to continue for the next two weeks prior to paving.

The first layer of asphalt has been installed on eastbound High House. New curb and gutter will be poured and additional asphalt placed over the next two weeks.

SB CP Grading (Custom)

Construction Update - June 28, 2018

On northbound Cary Parkway, we have installed the asphalt base, the first of three layers of asphalt to be placed. New curb and gutter has also been installed. 

Grading is almost complete on eastbound High House, and we will soon progress to southbound Cary Parkway. Additional asphalt and curb and gutter is expected to be complete within the next two weeks.

Lane closures are not allowed on July 3 and 4 to reduce traffic interruptions during the Independence Day holiday.

NB CP - Base and CG (Custom) (Custom)

 Construction Update - June 15, 2018

Asphalt base and new curb and gutter has been installed on the westbound High House Road approach. Grading has begun on the northbound High House Road approach and the asphalt base and curb and gutter is scheduled to be completed in two weeks. Grading will then progress to the eastbound High House Road approach. New fiber optic cable has been installed throughout the project area to run traffic signals and Town communications. This new cable is scheduled to be spliced into service during the week of June 18.

IMG_2192