Live Traffic Map

  

What's Happening Now

Construction Update - November 9, 2018

Weather permitting, the existing asphalt will be milled beginning November 12. The new, final layer of asphalt is scheduled to be paved starting November 19. It is expected to take two to three weeks to complete this work. Final signal work is also expected to begin November 12. Landscaping has begun and completed along the medians of High House Road.

The new pedestrian bridge being constructed as part of the SW Cary Parkway Pedestrian Bridge and Sidewalk Project is expected to be set on November 17. Check out the project web page for more information.

Landscaped Median web

Construction Update - October 26, 2018

We have begun construction of the new decorative bus shelter along westbound High House Road. Final paving and signal work is scheduled to start in two to four weeks. Duke Energy Progress continues to perform underground utility work and has installed some street lights.   

Construction Update - October 12, 2018

Most of the curb and gutter and asphalt has been completed in the median of Cary Parkway. Over the next couple of weeks masonry work and initial prep for the new signal pole foundations will begin.  Installation of new street lights is ongoing.

 NB CP Median