Live Traffic Map

  

What's Happening Now

Construction Update - December 28, 2018

With the opening of the new left and right turn lanes, we have begun installation of the aesthetic enhancements, including the decorative, stamped brick crosswalks and bus shelter. Duke Energy Progress has also installed most of the pedestrian level decorative lighting. These features will add unique visual elements to this intersection.

Bus and Crosswalk for website

Construction Update - December 14, 2018

We have opened the newly construction left turn lanes, which are expected to reduce congestion at the intersection. In the coming weeks, the contractor will install permanent pavement markings, stamped brick crosswalks, landscaping and a unique bus shelter as weather allows. There will be no lane closures allowed from 7 a.m. December 21 to 9:30 a.m. January 2 for the holidays.

Construction Update - December 7, 2018

Weather permitting, the newly constructed left turn lanes at Cary Parkway and High House Road are scheduled to be opened next week. There will be intermittent lane closures thorough early next year as weather allows to complete permanent pavement markings and signage, landscaping, bus shelter installation, and decorative traffic signal installation.

Construction Update - November 30, 2018

Asphalt milling and paving is ongoing and expected to be completed the week of December 3. Over the next couple of weeks the permanent pavement markings, landscaping, signal and bus shelter work is expected as we prepare to open all lanes of travel by the end of the year.

Roller CPHH Website

Construction Update - November 9, 2018

Weather permitting, the existing asphalt will be milled beginning November 12. The new, final layer of asphalt is scheduled to be paved starting November 19. It is expected to take two to three weeks to complete this work. Final signal work is also expected to begin November 12. Landscaping has begun and completed along the medians of High House Road.

The new pedestrian bridge being constructed as part of the SW Cary Parkway Pedestrian Bridge and Sidewalk Project is expected to be set on November 17. Check out the project web page for more information.

Landscaped Median web

Construction Update - October 26, 2018

We have begun construction of the new decorative bus shelter along westbound High House Road. Final paving and signal work is scheduled to start in two to four weeks. Duke Energy Progress continues to perform underground utility work and has installed some street lights.   

Construction Update - October 12, 2018

Most of the curb and gutter and asphalt has been completed in the median of Cary Parkway. Over the next couple of weeks masonry work and initial prep for the new signal pole foundations will begin.  Installation of new street lights is ongoing.

NB CP Median