Reclaimed Water Projects

Print
Press Enter to show all options, press Tab go to next option
RSS

Green Hope School Road Reclaimed Waterline Project

Overview: This project extends the Town’s existing reclaimed water system from west of NC 540 Hwy to the reclaimed water service areas located east of the highway. It also includes 2,000 feet of 16-inch pipe and 350 feet of 12-inch pipe along Green Hope School Road between Brooks Park Ln. and Highcroft Dr., as well as a proposed horizontal directional drill across NC 540 Hwy.  

Schedule: Project design has been completed. Construction is scheduled to begin spring 2019. 

Contact
Shuyan Tian, PE
Senior Engineer
(919) 469-4381
Shuyan.Tian@townofcary.org