White Oak Creek Greenway Project, Ph IV - MacArthur Drive to Davis Drive Segment

Print
Press Enter to show all options, press Tab go to next option
RSS

Project Update: November 27, 2019

The tunnel end-walls have both been poured.  Work continues on the boardwalk and site grading.  Planting and modifications to crosswalks at the Davis Drive/Park Village Drive intersection are scheduled to start in mid-December. The project will be closed Thanksgiving weekend but contractor plans to work subsequent Saturdays to keep the project on schedule.

Excavator working on construction site

White Oak Creek Greenway Tunnel interior looking out

Construction workers in muddy construction site

White Oak Creek Greenway drainage tunnel

White Oak Creek Greenway Boardwalk

Project Update: October 16, 2019

The round-the-clock tunnel boring operation was completed ahead of schedule on October 4. Work is now progressing on the concrete tunnel end-walls and the boardwalk. The contractor has driven most of the piles and is now installing the beams and decking. The contractor plans to work Saturdays to keep the project on schedule. 

White Oak Creek Greenway

Construction on White Oak Creek Greenway

Project Background

Together, the White Oak Creek Greenway and Black Creek Greenway constitute the spine of the Town of Cary’s greenway system, totaling 14.5 miles of continuous trails that link multiple local, county and state recreational lands and facilities, four school sites, and numerous residential, shopping and employment areas. The White Oak Creek Greenway is a 7.3-mile-long trail connecting the Wake County section of the American Tobacco Trail (near the Wimberly Road trailhead) to Bond Park in Cary. In Bond Park, the White Oak joins the Black Creek Greenway and further connects to Wake County’s Lake Crabtree Park, Umstead State Park and Raleigh’s Capital Area Greenway system via Umstead. The White Oak/Black Creek Greenway corridor has been designated as a primary segment of the East Coast Greenway (ECG).

The White Oak Creek Greenway has been on the Town of Cary’s master plan since 1995. Construction of the greenway began that year, and 95 percent of the trail -- almost seven miles  -- has been completed to date. This project addresses the final gap between MacArthur Drive and Davis Drive; a short but challenging segment that will require crossing a CSX rail line and Davis Drive. The two mile section of the trail that connects to the ATT through Wake County and Town of Apex jurisdiction, opened in Fall 2018. 

Project Scope

The 0.4-mile corridor between MacArthur Drive and Davis Drive is the last missing segments of the 7.3-mile White Oak Creek Greenway. This project will include design and construction of trail to close that gap. This segment of trail will pass through Davis Drive Park, which is located between the rail line and Davis Drive, under the rail line, and through Parkway Community Association open space to MacArthur Drive. The current project includes a grade-separated trail crossing under the CSX rail line. The Davis Drive crossing is planned to be on-grade at the existing traffic light at the park entrance in this phase of construction. Long term plans call for design and construction of a grade-separated trail crossing under Davis Drive.

Project Cost and Schedule

The project budget is $8.6 million for design and construction, provided by a combination of federal funding through the Locally Administered Projects Program (LAPP), 2012 Cary Community Investment Bonds, and Town capital project funds.  This includes an additional $1.85 million in LAPP funding recently allocated to this project in response to higher construction bids and associated construction costs.

Schedule

Bids were received on October 17, 2018.

Anticipated Construction Period: Spring 2019 - Summer 2020

Contact

Amy Mackintosh, ASLA
Landscape Architect
Transportation & Facilities Department
Town of Cary
(919) 460-4973
amy.mackintosh@townofcary.org