Intersection Improvements to Begin November 5 at NW Cary Parkway and Evans Road

Post Date:10/29/2018 10:34 AM
  • Weather permitting, contractors working on behalf of the Town of Cary will begin construction at the intersection of NW Cary Parkway and Evans Road on November 5
  • For the first phase of the project, the right lane of southbound Evans Road will be closed from Passport Way to the intersection to construct the new right turn lane.
  • Citizens can anticipate daytime closures from 9 a.m. to 4 p.m. Monday through Friday.

Cary, NC – Weather permitting, contractors working on behalf of the Town of Cary will begin construction to improve the flow of traffic, as well as pedestrian and vehicular safety at the intersection of NW Cary Parkway and Evans Road on November 5. Message boards will be installed a week before the start of construction notifying the public of the project.

Improvements include the construction of a new right turn lane along southbound Evans Road and a new left turn lane along eastbound NW Cary Parkway to improve operations and safety. New pedestrian crosswalks will also be added.

Citizens can anticipate daytime closures from 9 a.m. to 4 p.m. Monday through Friday. For the first phase of the project, the right lane of southbound Evans Road will be closed from Passport Way to the intersection to construct the new right turn lane. Drivers traveling through the area should expect minor delays and follow the direction of posted signs.

The left lane of westbound NW Cary Parkway will be closed from Carywood Drive to the intersection for phase two to construct the new left turn lane. The project is expected to be complete by spring 2019.

For more information, search “Evans Road and Cary Parkway Improvements” at www.townofcary.org.

To receive notice of traffic implications related to this and other projects, go to www.townofcary.org/email and subscribe to the News, Events, and Alerts list. For real-time traffic updates, visit “Alerts and Closures” at www.townofcary.org, follow the Town of Cary on Twitter @TOC_Traffic and navigate via the Waze app on your smartphone.

 

###

 

Primary Contacts

Sammy Wood, Engineer, (919) 380-4204
Kathryn Trogdon, Public Information Specialist, (919) 380-4227
Deanna Hawkes, Deputy Public Information Officer, (919) 380-4240

Resources

Phase 1 Map

 Phase 1 Map

Phase 2

 Phase 2 map

Evans Road and Cary Parkway Intersection Improvement Project
Alerts and Closures
Town of Cary Email Notifications
Town of Cary Traffic Feed on Twitter
Waze Traffic and Navigation App

Return to full list >>