STAFF REPORT

Operations Committee, December 11, 2006

Cary Aquatic Center Plan Development Process (PR07-14)
Consideration of the proposed approach and schedule for the site selection and development of the
Cary Aquatic Center
Speaker:  Mary G. Henderson, PRCR Director

 

From:  Mary G. Henderson, PRCR Director
Prepared by: Mary G. Henderson, PRCR Director
Approved by:  William B. Coleman, Jr., Town Manager
Approved by:  Benjamin T. Shivar, Assistant Town Manager

 

Introduction

At the work session on November 8, 2006, Town Council voted to pursue a regional aquatics venue concept for the Town.  This decision was conditional upon a private group—Friends of the Town of Cary Aquatics Center—making a commitment to and creating a fundraising plan to contribute at least $5 million of the facility’s expected $30 million capital cost.  Council approved an aquatic facility that would include an outdoor recreation pool, an indoor recreation pool, and an indoor 50 meter-by-25 yard competition pool with spring board diving and seating for 1,000 spectators.  A detail of the facility components and cost estimate is included in Attachment 1.  The estimate does not include the cost of land.  While no specific location was identified for this facility, the Town Council directed staff to analyze vacant sites of at least 15 acres in the north Cary area, including but not limited to a 30-acre parcel owned by the Town across from its existing North Cary Park near the intersection of Cary Parkway and Norwell Boulevard.  Council directed Town staff to develop a proposal for how to proceed with the project, starting with a site analysis process plan and present to Council in December, 2006.

 

Proposed Plan Process

In order to initiate the project, staff recommends that a Request for Proposals be developed and released so that a design team can be hired.  Staff proposes two distinct phases for the project.  Phase I would include identifying a preferred site in north Cary, completing a space program for the aquatic facility, providing preliminary project cost estimates, and completing a master plan of the facility on the preferred site. During Phase I staff will return to Council for final site selection and to approve the master plan for the proposed aquatic center.

 

The composition of the design team will consist of an architectural firm and, at a minimum, engineering consultants as well as an expert in the field of aquatics.  It is expected that the Town will contract directly with the architectural firm as the project lead. (If Council directs staff to proceed w/ Phase II, it is intended that the design team will be contracted to also complete Phase II.)

 

Phase I will include the following tasks:

 

Phase II will include design development, bidding, and construction administration as follows:

 

Private Fundraising

Staff has met once since the work session with Hill Carrow, Friends of the Cary Aquatic Facility, to initiate discussions about the development of the fund-raising plan.  The plan is being developed to secure both individual and corporate dollars.   It is recommended that the fund raising plan, as developed by Friends of the Cary Aquatic Facility, be presented to Council for approval at the time that the design team recommendation is also presented to Council for approval.  Progress reports will be provided, unless otherwise requested by Council, at each time that the project is presented to Council for review and consideration as recommended below.

 

Public Input

As with all Town projects, public input will be an important element of the planning process.  Opportunities for public input during Phase I are recommended as follows:

  1. Public input meeting to comment on the site selection.
  2. PRCR Advisory Board review and recommendation of site.
  3. Public input meeting to refine programming.
  4. PRCR Advisory Board review and recommendation of Master Plan.

During Phase II, the following opportunities are recommended:

1.      Public input meeting prior to final site plan approval.

2.      Public input meeting to comment on the business plan.

3.      PRCR Advisory Board review and recommendation of the business plan.

 

Next Steps

Staff recommends that the project be brought to Council in the time frame estimated below for further consideration as the following tasks are completed:

  1. Council approval of the design team, fund-raising plan (April 2007).
  2. Council approval of site selection, update on private fund-raising, and related additional appropriation of land costs if necessary (August 2007).
  3. Council approval of the Master Plan at the conclusion of Phase 1, contract for Phase II design, and update on private fund-raising (October 2007).
  4. Bid Award (October 2008)

 

The entire planning, design and ultimately construction of the Cary Aquatic Center is expected to take approximately three years and be completed in late 2009.

 

Fiscal Impact:  Capital costs are estimated to be $30 million (details provided in Attachment 1 below).  Staff recommends that the Town contract with the design team for Phase 1 initially, and, upon direction to move forward with the project, contract with the design team for Phase II.  Capital costs and the business will be refined as the project proceeds.  The annual operating cash flow, as previously presented to Council, is expected to be approximately negative $300,000.

 

Staff Recommendation:  Staff recommends approval of the proposed phasing, process, and schedule for the Cary Aquatic Center as presented.


 

ATTACHMENT 1

Detailed Cost Estimate

 

Unit

Sq. Ft.

Opinion of Cost

 

Demolition

 

 

$0

 

Public Spaces

 

8,130

 

$1,641,500

             Lobby

1,500

 

             Control / Cashier

180

 

             Administrative Offices (2)

250

 

             Vending / Concession Area

800

 

             Restrooms M/W (2)

1,000

 

             Locker Rooms

4,000

 

             Family Changing Room (2)

400

 

 

Aquatic Center

41,155

$12,649,050

             50 Meter X 25 Yard

12,750

 

                 Bulkhead

1

 

                 Moveable Floor

1

 

                 Springboard Diving

4

 

                 Spectator Seating (1000)

6,000

 

                 Meet Management Review

750

 

             Competitive Natatorium

22,155

 

             Recreation Pool

5,800

 

                 Participatory Play Feature

1

 

                 Current channel

2

 

                 Vortex

1

 

                 Waterslide

1

 

                 Spa

200

 

             Leisure Natatorium

9,500

 

             Storage

1,000

 

             Pool Mechanical Room

2,500

 

 

Fitness

2,250

$380,500

             Fitness Area

2,000

 

             Fitness Control Desk

200

 

             Fitness Storage

50

 

 

Administrative Support

1,670

$288,500

             Director Office

200

 

             Superintendent Office

120

 

             Supervisor Office (2)

250

 

             Intern Workstations

400

 

             Work Room

350

 

             Conference Room

350

 

 

Building Support

2,780

$446,500

             Building Mechanical

2,000

 

             Electrical

500

 

             Janitor

100

 

             Elevator

80

 

             Elevator Machine

100

 

 

Efficiency

11,197

$1,679,550

             Circulation and Walls (20%)

11,197

 

 

Total Building Construction Costs

67,182

$17,085,600

 

Site Construction Costs (parking lot, landscaping, utilities, walks)

 

$1,679,550

 

Furnishings & Equipment

 

$500,000

Subtotal

 

$19,265,150

 

Inflation (2 year)

10%

$1,926,515

 

 

 

Contingency

10%

$2,119,167

 

 

 

Indirect Costs

9%

$2,097,975

 

 

 

Outdoor Aquatics

 

$4,260,000

 

 

 

Total Estimated Project Costs:

 

$29,668,806

Say

 

$29,669,000