FOR INTERNAL USE September 10, 2001
CARY WALNUT STREET WIDENING GROUNDBREAKING
WHAT:
WHEN: 10:00 AM Tuesday, September 11th
WHERE: 2617 Walnut Street (approximately 0.1 mile on the right) just south of the Centrum
WHO: Town of Cary
BACKGROUND:
Approved by Cary voters in the 1999 Cary Community Bonds Referendum, this $5.3 million project begins about 1500 feet east of Dillard Drive and continues to Holly Springs Road. This project is a six lane median-divided roadway and includes realigning the Walnut Street /Tryon Road intersection. Walnut Street is a major east/west thoroughfare that runs from the east/southeast edge of town to downtown, with traffic counts of 20,000-30,000 vehicles per day.
###
|
PRIMARY CONTACTS: |
Joe Moore, Cary Engineering Services Manager, 919-469-4035 |