walker street extn.

Overview (Spring 2009)

The Town of Cary plans to extend Walker Street 1,200 feet from its current end at Cedar Street northwards to Chapel Hill Road. The project includes a grade-separated railroad crossing and realignment of cross streets.

View maps of the proposed road extension area: Option 1 / Option 2 / Option 3 / Option 4

View renderings of the proposed extension: Image 1/ Image 2 / Image 3 / Image 4

Schedule

Milestone

Date

Project Kick Off

Summer 2007

Public Information Exchange No. 1

March 24, 2008

Public Information Exchange No. 2

Spring 2009

Roadway & Structure Design complete

Summer 2014

Right-of-way & easement acquisition complete

Fall 2014

Construction begins

Winter 2014

Construction ends

Winter 2015

Cost

Congressman David Price has set aside $980,000 of Federal Funds towards this project for the Town of Cary.  The Town's Fiscal Year 2007 budget included $1.2 million for the preliminary planning of this project. The Fiscal Year 2008 Capital Improvements Plan indicates allocating an additional $1,050,000 in fiscal year 2009 and an additional $13,125,000 in fiscal year 2010 for easements and construction funding.

Contact

For questions, comments, or to see other information regarding this project contact:
Eric Simpson, P.E.
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-4204