| ![]() |
| Tryon Road Widening Construction Journal March/April 2008 With temperatures starting to rise and daylight hours increasing the construction crews are gearing up to make the final push to completion this summer. The three critical areas of the project are detailed below. 1. Lynn’s Branch Culvert (near Cary Parkway): The double-box culvert at Lynn’s Branch is complete. The pictures below show the fill being placed and compacted over the new culvert. Crews will now start to build up the 18” pavement section, the concrete curb and gutter, the 5’ wide sidewalk, and the 18’ wide median.
2. Long Branch Culvert (between Kielser Drive and Thornewood Drive):
With the completion of the northern portion of both culverts, crews are continuing to grade and pave the north-side of Tryon Road. Crews are seen placing blocks and backfill on one of the projects three retaining walls. Each block is 3 ½ feet tall and deep. The roadbed for the west-bound traffic can be seen in the near left side of the picture, while the completed east-bound road is seen in the farther left side of the picture. |