The state maintains Evans Road, so the Town must submit plans for Department of Transportation review at various stages of the project. The following schedule is tentative.

Preliminary plan submittal (25 percent complete)

Winter 2001

Right-of-way plan submittal (75 percent complete)

Summer 2002

Begin right-of-way and easement negotiations

Fall 2003

Final plan submittal (100 percent complete)

Winter 2004

Complete right-of-way and easement negotiations;

receive Final approval of plans from NCDOT

Summer 2005

Begin construction

Spring 2007

Complete construction

Spring 2008