TOWN OF CARY
STAFF REPORT

Davis Drive Widening Project (DS00-191)
Additional information on project as requested by Council.

Speaker
Tim Bailey

COMMITTEE MEETING

DATE

Operations Committee  
Planning & Development Committee  
TOWN COUNCIL MEETING

4/27/00

FROM: Tim Bailey, P.E., Engineering Division Director
Prepared by: Glen Harrell, EIT , Project Engineer
VIA: William B. Coleman, Jr., Town Manager
Benjamin T. Shivar, Assistant Town Manager

REVIEW: Staff has previously presented the results of a cost-benefit analysis of three potential cross sections for the Davis Drive corridor (see DS00-166). These comparisons have been based on traffic projections from the Capital Area Metropolitan Planning Organization (CAMPO) traffic model and construction cost estimators. Council has requested additional information regarding utilizing a four-lane section with a 16’ median for the portion of the corridor between High House Rd. and Morrisville-Carpenter Rd.

This report includes additional information regarding the following:

Median Widths - NCDOT standards require that raised median sections be a minimum of 16’ to provide for a continuous roadway section and to allow for 12’ turn lanes while maintaining a 4’ median between opposing traffic. (Please note that the current 4’ median design is a compromise with NCDOT to provide separation between opposing traffic while maintaining as much of the existing infrastructure as possible.) The 16’ median does not provide space for vehicles to make left turns onto the roadway in two movements. AASHTO recommends median widths of at least 30’ so that drivers are not encouraged to attempt to make a left turn in two independent movements without being fully protected from opposing traffic.

The project length from High House Rd. to just north of Morrisville-Carpenter Rd. is 2.99 mi. Approximately 2/3 of this length will have a full width median while the remaining 1/3 will have reduced or no median due to turn lanes and intersections. If, in the future, an additional lane (even a reversible lane) were required, the 16’ median would provide adequate space for construction without acquiring additional R/W.

Pedestrian / Bikeways – The Town of Cary PRCR Division recommends a 10’ width for corridors shared between pedestrians and bicycles. The costs are comparable between a 10’ asphalt path and a 5’ concrete sidewalk. Also, if a 16’ median section were utilized, the 10’ Pedestrian / Bikeway would fit within a100’ R/W, which was the R/W required for the five-lane section in the earlier analyses. Bike lanes behind the curb will typically be used more by the recreational cyclist. However, alternate bike routes are being proposed for cyclists commuting through the area.

 

Land Use and Municipal Boundaries – The figures below indicate the Town Limits and Current Land Use in the area.

 

 

 

Cost and Proximity comparisons of utilizing a 16’ grassed median between High House Rd. and Morrisville-Carpenter Rd vs. existing 4’ concrete median design.

Cost and proximity comparisons of the earlier analyses were based on each cross section being utilized for a corridor length of 4.5 mi. This comparison differs by focusing only on the 2.99 mi. section of the corridor between High House Rd. and Morrisville-Carpenter Rd.

 

Additional required R/W and proximity damages - This cross section will require a 99’ R/W if the 10’ pedestrian / bikeway is utilized. The current design is based on the existing Thoroughfare plan and requires a 78’ R/W section. The proximity damages for he 16’ median section are nearly identical to the 100’ R/W (5-lane section) in the earlier analyses. The 99’ R/W will cost approximately $1,000,000 more than the existing design, as it did in the earlier analyses because most of these costs were incurred north of High House Rd.

Comparison of Paved Area – The amount of paved area per linear foot of roadway for the 16’ median section is identical to the current design. The only difference is that some of the "green area" is in the center of the roadway for the 16’ median section instead of behind the sidewalks in the current design.

Construction Costs – It should be noted that one of the assumptions in the original analysis was that the typical section extends for a corridor length of 4.5 miles. This assumption is no longer valid, and the following comparison of construction costs between these two sections is based on more project specific data for the 2.99 mile section of Davis Drive. The following comparisons indicate that the construction costs will be approximately $429,000 more for the 16’ median section.

 

 

Based on the above analysis, the 16’ median section will have a total cost of approximately $1.4M more than the existing design.

Staff Recommendation: Staff recommends proceeding with the project as currently designed (four lanes with 4’ monolithic median and turn lanes as required) with the following modifications:
  1. Modifications required by NCDOT reviews,
  2. Addition of Jump-Queue-Through lanes at Morrisville-Carpenter Rd. Intersection, and
  3. If directed by Town Council, the addition of a 16’ landscaped median and the replacement of one sidewalk with a 10’ pedestrian / bike lane between High house Rd. and Morrisville-Carpenter Rd.

Staff further recommends that the Thoroughfare Plan be amended to change Davis Drive to a six-lane section with a 30’ median north of Morrisville-Carpenter Road, so that future development will accommodate this cross section.