TOWN OF CARY
REQUEST FOR REZONING/COMPREHENSIVE PLAN AMENDMENT
PLANNING AND ZONING BOARD
APPLICANT(S) |
OWNER(S) |
| Jerry Turner & Associates 905 Jones Franklin Road Raleigh, NC 27606 (919) 851-7150 (919) 851-7547 |
Hilda Carpenter 1709 Morrisville Carpenter Road Morrisville, NC (919) 467-8434 |
| LOCATION: | Carpenter Upchurch Road, north of SR1621 |
| MAPS: | Vicinity Zoning Land Use Plan |
In Town Limits [ ] Cary ETJ [ X ]
PROPOSED SCHEDULE OF MEETINGS |
|
| TOWN COUNCIL PUBLIC HEARING: | May 13, 1999 |
| PLANNING & ZONING BOARD: | June 21, 1999 |
| TOWN COUNCIL: | July 8, 1999 |
PARCEL INFORMATION |
||
Parcel # |
Realid # |
Area |
073504806895 |
0011746 |
52.11 acres |
REZONING DATA |
CURRENT |
PROPOSED |
|
| Zoning: | Residential 12 Conditional Use, Residential Multi Family-8 Conditional Use, Residential Multi Family-12 Conditional Use, Office and Institutional Conditional Use, Business 2 Conditional Use | Amended conditions |
| Overlay District: | N/A |
N/A |
| Land Use: |
REZONING CONDITIONS |
|
CURRENT |
PROPOSED |
OVERALL
|
|
| A. R-12 CU Tract - (8.05 acres
7.85 acres net) 1. A street and pedestrian stubout will be provided to connect to the R-12 CU tract to the south. 2. One (1) right-in/right-out access from the proposed Morrisville Parkway 3. Along the north-south creek (between the proposed R-12 CU and the proposed R-MF8 CU) a 50 foot greenway corridor (along the sewer easement) will be offered to the Town at the time of need or at the time of first site/subdivision submittal (whichever comes first). 4. A pedestrian connection will be provided to the greenway along the adjacent creek (which would provide a connection to the R-MF8CU tract). |
A. R-12 CU
Tract - (8.05 acres 7.85 acres net)
3. Along the north-south creek (between the proposed R-12 CU and the proposed R-MF8 CU) a 50 foot greenway corridor (along the sewer easement) will be offered to the Town at the time of need or at the time of first site/subdivision submittal (whichever comes first). 4. A pedestrian connection will be provided to the greenway along the adjacent creek (which would provide a connection to the R-MF8CU tract). |
| B. RMF-8 CU Tract - (9.12 acres
7.54 net) 1. One (1) right-in/right-out access from proposed Morrisville Parkway 2. One (1) full service access from the proposed Alston Avenue 3. Maximum of six (6) dwelling units per acre. 4. A pedestrian connection will be provided to the greenway along the adjacent creek (which would provide a connection to the R-12CU tract). |
B. RMF-8 CU
Tract - (9.12 acres 7.54 net)
3. Maximum of six (6) dwelling units per acre. 4. A pedestrian connection will be provided to the greenway along the adjacent creek (which would provide a connection to the R-12CU tract). |
| C. R-MF-12 CU Tract - (12.34
acres; 10.78 acres net) 1. A driveway and pedestrian stubout will be provided to connect to the B-2 CU tract to the west. 2. One (1) right-in/right-out access from the proposed Morrisville Parkway. 3. One (1) full service access from the proposed Alston Avenue. 4. A driveway and pedestrian stubout will be provided to connect to the R-MF-8 CU tract to the south. |
C. R-MF-12 CU
Tract - (12.34 acres; 10.78 acres net) 1. A driveway and pedestrian stubout will be provided to connect to the B-2 CU tract to the west.
4. |
| D. B-2 CU Tract - (13.33 acres
12.33 acres net) 1. Two (2) right-in/right-out accesses from proposed Morrisville parkway 2. One (1) full service access to Carpenter Upchurch Road 3. At the time of the first site plan submittal within any of the tract, on overall (conceptual) plan will be submitted for the entire tract. 4. The tract will be designed with a village (pedestrian friendly) concept. No single tenants or big box uses (over 40,000 sq. ft.) other than a supermarket (up to 60,000 s. ft.) will be allowed. 5. All buildings proposed for the tract will be architecturally compatible with each other. Specifically the materials, color and general design of the buildings will be compatible. 6. A 50 (Type B) buffer will be provided where the tract is adjacent to the RMF-12 CU property to the south 7. A 20 (Type B) buffer will be provided where the B-2CU adjoins the RMF-12CU tract to the east 8. A driveway and pedestrian stubout will be provided to connect to the RMF-12CU property to the east and to the south. 9. Some small amount of public outdoor space such as an outdoor mini-plaza, mini-park or other space will be included in the design of the B-2CU area. |
D. B-2 CU Tract
- (13.33 acres 12.33 acres net)
3. At the time of the first site plan submittal within any of the tract, on overall (conceptual) plan will be submitted for the entire tract. 4. The tract will be designed with a village (pedestrian friendly) concept. No single tenants or big box uses (over 40,000 sq. ft.) other than a supermarket (up to 60,000 s. ft.) will be allowed. 5. All buildings proposed for the tract will be architecturally compatible with each other. Specifically the materials, color and general design of the buildings will be compatible. 6. A 50 (Type B) buffer will be provided where the tract is adjacent to the RMF-12 CU property to the south 7. A 20 (Type B) buffer will be provided where the B-2CU adjoins the RMF-12CU tract to the east
9. Some small amount of public outdoor space such as an outdoor mini-plaza, mini-park or other space will be included in the design of the B-2CU area. |
| E. O & I CU (11.16 acres
10.11 acres net) 1. Two (2) right-in/right-out accesses from the proposed Morrisville Parkway. 2. A 50 (Type B) buffer will be provided along the north and east property lines. 3. A street stubout will be provided to connect to the property to the east. 4. All buildings proposed for the tract will be architecturally compatible with each other and to the B-2CU tract buildings across Morrisville Parkway. |
E. O & I CU
(11.16 acres 10.11 acres net)
2. A 50 (Type B) buffer will be provided along the north and east property lines. 3. A street stubout will be provided to connect to the property to the east. 4. All buildings proposed for the tract will be architecturally compatible with each other and to the B-2CU tract buildings across Morrisville Parkway. |
REZONING HISTORY |
| Case 97rez12 |
| From Residential 30 Zoning To Residential 12 CU, Residential Multi Family 8 CU, Residential Multi Family 12 CU, Office and Institutional CU, Business 2 CU Zoning |
| Approved by Town Council on: June 12, 1997 |
SITE DATA |
WATER/SEWER SERVICE |
| Staff Remarks: Water service for the property would be extended north along Carpenter Upchurch Road. Sewer Service is available to serve the property. |
TRANSPORTATION |
| Traffic Impact Analysis Required: Yes [ ] No [X] |
| Staff Remarks: Per the interim Planned Development Ordinance, a traffic impact analysis report would not be required at this time. However, when the initial site plan is submitted, a traffic impact analysis report is likely to be required. |
ENVIRONMENTAL CONSIDERATIONS |
| Staff Remarks: The subject property is in the Crabtree Watershed and is not required to comply with the towns watershed protection ordinance. |
WAKE COUNTY SCHOOL CAPACITY There shall be no additional impact to Wake County Schools |
ADJACENT ZONING AND LAND USES |
||
Zoning: |
Land Use: |
|
| North: | R30 | Residential and Vacant |
| South: | RM-CU | Residential Heritage Pines |
| East: | RMF-8 and R-30C | Preston Village North and Lake Ridge Town Homes |
| West: | R-40 and PEC | Residential and Vacant |
TOWN OF CARY FUTURE LAND USE PLAN DATA |
CURRENT |
PROPOSED |
|
| Plan Designation: | Low Density Residential High Density Residential Office/Institutional Commercial |
No Change |
| Alternate Designation: | None | No Change |
| Activity Center: | Neighborhood Activity Center | No Change |
EXISTING LAND USE PLAN AMENDMENT HISTORY |
| Case 97-REZ-12 From Low Density Residential and an alternate Neighborhood Activity Center to a Neighborhood Activity Center with a mix of Low Density Residential, High Density Residential, Office/Institutional, and Commercial Approved by Town Council on: June 12, 1997 |
STAFF ANALYSIS AND RECOMMENDATION |
| CHANGES SINCE PUBLIC HEARING: *Yes [ X ] No [ ] |
| *See revised rezoning conditions. |
| PROTEST PETITION FILED: Valid [ ] Invalid [ ] None Filed [ X ] |
REZONING REQUEST |
| Analysis: In 1998 the Town of Cary
approved a rezoning and site plan contiguous to the southern boundary of this tract. This
project, Heritage Pines, does not contain any access points to the tract being reviewed
for rezoning. The current zoning conditions for the property require that access points be provided in the design of this tract. The applicant is requesting that all these access points be deleted in order to avoid the conflict of design along the southern boundary. Staff has reviewed the request with the applicant and suggests all pedestrian access points and the access to the nonresidential remain. The applicant has amended the conditions to reflect staffs suggestion. Recommendation: Staff recommends approval. |
PLANNING & ZONING BOARD RECOMMENDATION |
| At their meeting of June 21, 1999, the Planning and Zoning Board voted to forward this request to Town Council with a recommendation of approval. |