TOWN OF CARY Text Box: UTILITY CAPITAL IMPROVEMENTS
FISCAL YEAR 2008 UTILITY CAPITAL IMPROVEMENTS
SEWER CAPITAL IMPROVEMENTS FUND
A. $5,825,000 Biosolids Aeration System Improvements
B. $330,000 Campbell Road Interceptor
C. $300,000 Crabtree Interceptor/York Interceptor Capacity Improvements
D. $3,600,000   Force Main Inspection and Rehabilitation
E. $500,000 Green Level Interceptor
F. $402,000 Kit Creek Basin Sanitary Sewers
G. $2,003,000 Morrisville Merger - Kit Creek Basin Sanitary Sewers
H. $102,000 Morrisville Merger - Northwest Cary Wastewater Conveyance to WWRWRF
I. $80,250 Morrisville Merger - Reclaimed Water Line Oversizing
J. $580,650 Morrisville Merger - Replacement/Rehabilitation of Existing Sewer Mains - Morrisville
K. $42,800 Morrisville Merger - Sanitary Sewer Oversizing - Morrisville
L. $590,000 Morrisville Public Works and Perimeter Park Barscreen Addition
M. $2,306,000 Northwest Area Reclaimed Water Project - Phase II
N. $525,000 Northwest Area Reclaimed Water Project - Phase III
O. $99,600 Northwest Cary Force Main Diversions
P. $150,000 Pirates Cove Sanitary Sewer Rehabilitation
Q. $102,600 Reclaimed Water Line Oversizing
R. $80,000 Reedy Creek Pump Station Elimination
S. $739,000 Replacement/Rehabilitation of Existing Sewer Mains
T. $107,000 Sanitary Sewer Oversizings
U. $570,000 Sewer System Master Plan
V. $100,000   Swift Creek Crossing Gravity Sewer Extension
W. $6,520,000 Swift Creek Pump Station Parallel Force Main
X. $490,000 Swift Creek Regional Pumping Station Improvements (Existing Equipment Improvements)
Y. $110,000 Town Hall Drive Pump Station Elimination
Z. $415,000 Upper Camp Branch Interceptor
AA. $315,000 Walnut Creek Pump Station Electrical Improvements
AB. $800,000 Wastewater Pump Station Improvements
AC. $710,000 Wastewater Pump Station Parallel Force Mains
AD. $139,000 Wastewater SCADA Project
AE. $140,000 Western Cary Collections System Odor Control
AF. $459,324 WWRWMF - Beaver Creek Pump Station and Force Main - APEX
AG. $757,156 WWRWMF - Beaver Creek Pump Station and Force Main - CARY
AH. $107,219 WWRWMF - Beaver Creek Pump Station and Force Main - MORRISVILLE
AI. $43,068,521 WWRWMF - New Water Reclamation Facility - APEX
AJ. $71,155,066 WWRWMF - New Water Reclamation Facility - CARY
AK. $10,108,172 WWRWMF - New Water Reclamation Facility - MORRISVILLE
AL. $180,609 WWRWMF - Project Management
AM. $27,603 WWRWMF - West Cary Pump Station Expansion and Force Main to New Water Reclamation Facility - APEX
AN. $649,708 WWRWMF - West Cary Pump Station Expansion and Force Main to New Water Reclamation Facility - CARY
AO. $92,890 WWRWMF - West Cary Pump Station Expansion and Force Main to New Water Reclamation Facility - MORRISVILLE
 
$155,380,168 Total
In the following individual project description pages, the estimated personnel, operating and maintenance impacts are provided to show a more comprehensive view of each project.  Some projects will be completed mid-year; the impact shown is for the first full year after the project is complete.  Any impact that begins after FY 2008 has been adjusted for inflation in the outer years.  Inflation is factored at 5% per year.  Some projects do not show annual impacts although there may be minor maintenance investments at various intervals after the project is complete.   
* WWRWMF = Western Wake Regional Wastewater Management Facility