Q.  WATER

 

 

PROJECT TITLE:   Triangle Parkway Water Conflicts

 

RESPONSIBLE DEPARTMENT:   Engineering

 

PROJECT FUNDING:   $501,540

 

FIRST YEAR ESTIMATED OPERATING COSTS:   None

 

PROJECT DESCRIPTION:

This project provides for the relocation, lowering, encasement and other modifications of existing water lines within the Triangle Parkway corridor.  The FY 2009 appropriation of $501,540 fully supports the project with no additional funding requests anticipated.

 

PROJECT JUSTIFICATION:

The water utilities described within the noted geographic area are sited via a North Carolina Department of Transportation encroachment agreement with the Town of Cary.  These water lines and their locations must be adjusted/modified before construction of the Triangle Parkway begins.

 

PROJECT LOCATION: