O.  WATER

 

 

PROJECT TITLE:   NC-540 Western Wake Parkway Water Conflicts

 

RESPONSIBLE DEPARTMENT:   Engineering

 

PROJECT FUNDING:   $3,641,460

 

FIRST YEAR ESTIMATED OPERATING COSTS:   None

 

PROJECT DESCRIPTION:

This project provides for the relocation, lowering, encasement, and other modifications of existing water lines within the NC-540 corridor between US-64 in Apex and NC-55 near the Durham county line.  The project also provides for the installation of new water lines as needed within this area.

 

The FY 2009 appropriation of $3,641,460 fully supports the NC-540 Western Wake Parkway Water Conflict project with no additional funding requests anticipated.

 

PROJECT JUSTIFICATION:

The water utilities described within the noted geographic area are sited via a North Carolina Department of Transportation encroachment agreement with the Town of Cary.  These water lines and their locations must be adjusted/modified before construction of the Western Wake Parkway begins.

 

PROJECT LOCATION: