K. WATER
|
PROJECT TITLE:
Large Valve Repair/Replacement |
|
|
|
RESPONSIBLE DEPARTMENT: Engineering |
|
|
|
PROJECT FUNDING:
$200,000 |
|
|
|
FIRST YEAR ESTIMATED OPERATING COSTS: None |
|
PROJECT DESCRIPTION: |
|
This
project provides for the repair and replacement of large valves in the Town’s
water distribution system. Large
valves are defined as being 30-inches in diameter or greater and are located
at key junctions in the water distribution system. Valves of this nature are typically used to
isolate pressure zones, long runs of large pipe, and sources of potable water. Total project cost is estimated to be
$400,000. Appropriations through FY
2008 total $200,000. The FY 2009
appropriation of $200,000 represents remaining funding necessary for project
completion. PROJECT JUSTIFICATION: The
failure of large diameter valves to operate as intended can cause
difficulties in the operation of the water system as system failures
typically occur at critical locations for isolation of large segments of the
system. The inability to reliably
isolate sections of the system may make it difficult, if not impossible, to
operate as intended and to properly maintain many portions of the system. |
|
PROJECT LOCATION: |
This project will occur throughout the Town of