PROJECT TITLE: |
|
|
|
RESPONSIBLE
DEPARTMENT: Engineering |
|
|
|
PROJECT FUNDING: $50,000 |
|
|
|
FIRST YEAR ESTIMATED
OPERATING COSTS: None |
|
PROJECT
DESCRIPTION: |
||
|
The
Eagle Meadow Court Water Line Connection provides 300 linear feet of 12-inch
water main connecting water lines at Heritage Pines Drive and PROJECT
JUSTIFICATION: This
project is essential to the Town’s ability to provide service redundancy in
the event of water line breaks or high fire fighting demand. It also provides a secondary feed and loop
to the service area. |
||
|
PROJECT
LOCATION:
|