TOWN OF CARY
FISCAL YEAR 2008 UTILITY CAPITAL IMPROVEMENTS
         WATER CAPITAL IMPROVEMENTS FUND
A. $6,800,000 Automated Meter Reading System
B. $2,800,000 Cary/Apex Water Treatment Plant - Phase II Pumping
C. $13,199,000 Cary/Apex Water Treatment Plant - Phase II Residuals and Chemical Feed Facilities
D. $200,000 Cary/Apex Water Treatment Plant - Phase III Expansion and Improvements (56 million gallons/day)
E. $70,000 Cary/Apex Water Treatment Plant Sodium Hypochlorite Tank Replacement
F. $65,400 Cross-Connection Control - Town Facilities
G. $900,000 Green Level Church Road Water Line - Phase I
H. $1,114,000 Green Level West Road Water Line - Phase I
I. $200,000 Large Valve Repair/Replacement
J. $51,360 Morrisville Merger - Morrisville Large Water Meter Replacements
K. $230,000 Morrisville Merger - Upgrade Water Lines
L. $150,000 Small Diameter Waterline Reinforcements
M. $250,000 South Harrison Avenue Water Line Extension
N. $415,800 Upgrade Water Lines
O. $1,090,000 Walnut Street Water Line Reinforcement
P. $102,600 Water Line Oversizings
Q. $107,000 Water Resource Planning and Management
R. $608,000 Water System Monitoring Protection Project
S. $1,416,000 Wimberley Road Water Line
 
$29,769,160 Total
In the following individual project description pages, the estimated personnel, operating and maintenance impacts are provided to show a more comprehensive view of each project.  Some projects will be completed mid-year;  the impact shown is for the first full year after the project is complete.  Any impact that begins after FY 2008 has been adjusted for inflation in the outer years.
Inflation is factored at 5% per year.  Some projects do not show annual impacts although there may be minor maintenance investments at various intervals after the project is complete.