Total Water System Bonds Approved - $66.5 million
Fall 2002 Update
Progress report on projects receiving 1999 water
bonds that are complete or in the pipeline
(Other sources of money also used for some projects)
| Project |
Bonds
Budgeted |
Status |
| Water
Treatment Plant |
$50,639,700 |
DONE |
| Plumtree
Way Storage Tank |
2,755,000 |
DONE |
| Old
Apex Road Storage Tank |
$85,000 |
DONE |
| SCADA
* |
$200,000 |
In
Design
Begin Construction
Fall 2003
Finish Construction
Spring 2004 |
| Carpenter
Storage Tank |
2,730,000 |
DONE |
| Cary
Towne Blvd. Storage Tank |
1,770,000 |
Design
- Not Yet Scheduled
Start Construction Fall 2008
Finish Construction Fall 2010 |
| Kildaire
Storage Tank (spheroid) |
$75,000 |
In
Design
Start construction Fall 2003
Finish construction
Spring 2005 |
* Supervisory Control and Data Acquisition (system
for centralized monitoring of data from water and wastewater facilities)
Water Bonds Background Information - Prepared
1999
The following was compiled to educate voters for
the February 1999 bond referendum.
Overview of Water Treatment Plant (WTP) Cost |
(in
Millions) |
For Regulatory Compliance |
$13.4 |
For Reliability Issues |
$16.3 |
For Plant Capacity Expansion |
$40.0 |
Total |
$69.7 |
Cary's Share of WTP Costs - 77% |
(in
Millions) |
For Regulatory Compliance |
$10.3 |
For Reliability Issues |
$12.6 |
For Plant Capacity Expansion |
$30.8 |
Total |
$53.7 |
Other Water System Related Bond Projects
Four (4) Elevated Water Storage Tanks costing $9.95 Milllion
WATER SYSTEM BONDS
SUMMARY
Description |
(in
Millions) |
Cary's Share of WTP Expansion |
$53.7 |
Four Elevated Water Storage Tanks |
$10.0 |
Capitalized Interest |
$6.5 |
Less Cash From Savings |
$3.7 |
Total Water System Bonds |
$66.5 |
Project
Components
for
Cary/Apex Water Treatment Facility
Expansion
to
40.0 MGD
| Raw Water Facilities - Provide
additional pumps at Raw Water Intake and a second raw water transmission pipeline to
convey the raw water from Jordan Lake to the plant. |
| |
| Rapid-Mix Chambers and Clarifiers - To
improve mixing of treatment chemicals and to add settling capacity. |
| |
| Filters - To increase filtering
capacity and upgrade existing units for improved taste and odor removal. |
| |
| Modified Chemical Facilities - To
increase feed capacity and redundancy, for improved process safety management and to meet
EPA risk management requirements. |
| |
| Hypochlorite Building - To increase
capacity and safety for applying disinfection residual. |
|
| Ozone Facilities - For maximum
disinfection, to meet new EPAs regulations by 2000 and 2003, and for taste and odor
control. |
|
| Clearwells - For improved disinfection
contact time and for increased treated water storage. |
|
| Sludge Facilities - To meet state
requirements and allow on-site dewatering for less costly disposal. |
|
| Electrical & Standby Power - To
upgrade power supply and to provide reliable electrical distribution with standby power. |
|
| Instrumentation/SCADA - For enhanced
plant automation and process control. |
|
| Finished Water Pump Station - To pump
water into the distribution system mains. |
|
| Finished Water Transmission Main - To
deliver water from the plant to the distribution system mains. |
Public Input Session Presentation
For further information, please call the Town at 469-4007, or Email us at townofcary@ci.cary.nc.us
|