Water Bonds Roadway Bonds Parks Bonds Aquatic Center Bonds Bonds Finance Public Input Bonds FAQ
















Total Water System Bonds Approved - $66.5 million

Fall 2002 Update

Progress report on projects receiving 1999 water bonds that are complete or in the pipeline

(Other sources of money also used for some projects)

Project

Bonds Budgeted

Status

Water Treatment Plant

$50,639,700

DONE

Plumtree Way Storage Tank

2,755,000

DONE

Old Apex Road Storage Tank

$85,000

DONE

SCADA *

$200,000

In Design

Begin Construction Fall 2003

Finish Construction Spring 2004

Carpenter Storage Tank

2,730,000

DONE

Cary Towne Blvd. Storage Tank

1,770,000

Design - Not Yet Scheduled

Start Construction Fall 2008

Finish Construction Fall 2010

Kildaire Storage Tank (spheroid)

$75,000

In Design

Start construction Fall 2003

Finish construction Spring 2005

* Supervisory Control and Data Acquisition (system for centralized monitoring of data from water and wastewater facilities)

 

Water Bonds Background Information - Prepared 1999

The following was compiled to educate voters for the February 1999 bond referendum.


Overview of Water Treatment Plant (WTP) Cost

(in Millions)

For Regulatory Compliance

$13.4

For Reliability Issues

$16.3

For Plant Capacity Expansion

$40.0

Total

$69.7


Cary's Share of WTP Costs - 77%

(in Millions)

For Regulatory Compliance

$10.3

For Reliability Issues

$12.6

For Plant Capacity Expansion

$30.8

Total

$53.7


Other Water System Related Bond Projects
Four (4) Elevated Water Storage Tanks costing $9.95 Milllion


WATER SYSTEM BONDS

SUMMARY

Description

(in Millions)

Cary's Share of WTP Expansion

$53.7

Four Elevated Water Storage Tanks

$10.0

Capitalized Interest

$6.5

Less Cash From Savings

$3.7

Total Water System Bonds

$66.5



 
Project Components
for
Cary/Apex Water Treatment Facility
Expansion
to
40.0 MGD 

Raw Water Facilities - Provide additional pumps at Raw Water Intake and a second raw water transmission pipeline to convey the raw water from Jordan Lake to the plant.
 
Rapid-Mix Chambers and Clarifiers - To improve mixing of treatment chemicals and to add settling capacity.
 
Filters - To increase filtering capacity and upgrade existing units for improved taste and odor removal.
 
Modified Chemical Facilities - To increase feed capacity and redundancy, for improved process safety management and to meet EPA risk management requirements.
 
Hypochlorite Building - To increase capacity and safety for applying disinfection residual.
Ozone Facilities - For maximum disinfection, to meet new EPA’s regulations by 2000 and 2003, and for taste and odor control.
Clearwells - For improved disinfection contact time and for increased treated water storage.
Sludge Facilities - To meet state requirements and allow on-site dewatering for less costly disposal.
Electrical & Standby Power - To upgrade power supply and to provide reliable electrical distribution with standby power.
Instrumentation/SCADA - For enhanced plant automation and process control.
Finished Water Pump Station - To pump water into the distribution system mains.
Finished Water Transmission Main - To deliver water from the plant to the distribution system mains.


Public Input Session Presentation

For further information, please call the Town at 469-4007, or Email us at townofcary@ci.cary.nc.us