Total Roadway Bonds Approved - $62.6 million

Fall 2002 Update

Progress report on projects receiving 1999 streets and sidewalks bonds that are complete or in the pipeline

Project

Bonds Budgeted

Schedule

Chapel Hill Road Widening

N.E. Maynard to Trinity Road

$900,000

Final Plans Spring 2003

Start Construction Spring 2004

Finish Construction Spring 2005

Davis Drive Widening

$7,000,000

Final Plan Approval Winter 2002

Start Construction Spring 2003

Finish Construction Spring 2005

Evans Road Widening

$440,000

Right-of-way Plan Summer 2002

Start Construction Fall 2004

Finish Construction Summer 2005

Evans Road/Chapel Hill Road

Realignment

$3,000,000

DONE

High House Road Widening

N.C. 55 To Carpenter Upchurch

$5,745,000

Final Plan Winter 2002

Start Construction Summer 2003

Finish Construction Late 2004

Kildaire Farm Widening

(Swift Creek To Penny Road)

4,670,000

Finish Design Spring 2003

Start Construction Fall 2004

Finish Construction Late 2005

Louis Stephens Drive Extension (Morrisville Parkway To ETJ*)

$2,800,000

Finalizing Design Fall 2002

Start Construction Spring 2003

Finish Construction Summer 2004

Maynard Road Widening

(Kildaire Farm To Seabrook)

$1,700,000

Done

Maynard Road Widening

(Kildaire Farm To West Chatham)

$3,855,000

Easement Negotiations Winter 2002

Start Construction Spring 2004

Finish Construction Spring 2005

Cary Parkway Lane Additions

$400,000

Done

Piney Plains Road Widening

$3,655,000

Start Construction Fall 2003

Sidewalks

 

Done

Street Improvements

$3,375,000

Done

Trinity Road Widening, Extension

N.C. 54 to Cary Towne Boulevard

$2,400,000

Initial Planning Fall 2002

Start Construction Summer 2005

Finish Construction Summer 2006

Tryon Road Widening

Kildaire Farm to Campbell Road

$5,025,000

Begin Acquiring Right-of-way Fall 2002

Start Construction Summer 2003

Finish Construction Summer 2005

US 1/64 & Walnut Street

Interchange

$6,000,000

Begin Acquiring Right-of-way Fall 2002

Start Construction Summer 2004

Finish Construction Summer 2006

US 1/64 Cary Parkway Interchange

$5,000,000

Begin Acquiring Right-of-way Fall 2002

Start Construction Summer 2004

Finish Construction Summer 2006

Walnut Street Improvements

$1,170,000

DONE

 

* Extra-Territorial Jurisdiction (Area Beyond Town Limits Where Town Planning And Zoning Authority Applies) 

Roadway Bonds Background Information - Prepared 1999

The following was compiled to educate voters for the February 1999 bond referendum:




$62.635 Million

Goals
  • Fully complete & widen loops
  • Alleviate traffic in congested areas
  • Improve & widen radial roadways
  • Consider alternate transportation modes
  • Safety of users
  • Improve level of service
  • Rely on NCDOT to improve interstates and freeways

Draft Projects
  • Adjustments can be made through the process
  • Address Town Council concerns
  • Make adjustments based on citizen feedback

Draft Project List
  • Walnut St. Improvements $6.2M
  • Evans Road Widening $1.155M
  • Street Improvements $5.0M
  • Maynard Road Widening - Ph 2 $2.07M
  • Tryon Road Widening $ 3.0M
  • Holly Springs Road Widening $3.8M
  • High House Road Widening $1.845M
  • Piney Plains Road Widening $3.165M
  • Davis Drive Widening $4.5M
  • Evans Road/Chapel Hill Road Realignment $3.0M
  • Aviation Parkway Widening $3.3M
  • N. Cary Parkway Lane Additions $5.4M
  • Cary Parkway Extension $9.3M
  • Trinity Road Widening & Extension $9.4M
  • Sidewalks Project $1.5M


Public Input Session Presentation

For further information, please call the Town at 469-4007, or Email us at townofcary@ci.cary.nc.us