![]() |
![]() | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Total Roadway Bonds Approved - $62.6 million Fall 2002 Update Progress report on projects receiving 1999 streets
and sidewalks bonds that are complete or in the pipeline Project Bonds
Budgeted Schedule Chapel
Hill Road Widening N.E. Maynard to Trinity Road $900,000 Final
Plans Spring 2003 Start Construction Spring
2004 Finish Construction
Spring 2005 Davis
Drive Widening $7,000,000 Final
Plan Approval Winter 2002 Start Construction Spring 2003 Finish Construction Spring 2005 Evans
Road Widening $440,000 Right-of-way
Plan Summer 2002 Start Construction Fall 2004 Finish Construction
Summer 2005 Evans
Road/Chapel Hill Road Realignment $3,000,000 DONE High
House Road Widening N.C. 55 To Carpenter Upchurch $5,745,000 Final
Plan Winter 2002 Start Construction Summer
2003 Finish Construction
Late 2004 Kildaire
Farm Widening (Swift Creek To Penny Road) 4,670,000 Finish
Design Spring 2003 Start Construction Fall
2004 Finish Construction
Late 2005 Louis
Stephens Drive Extension (Morrisville Parkway To ETJ*) $2,800,000 Finalizing
Design Fall 2002 Start Construction Spring 2003 Finish Construction Summer 2004 Maynard
Road Widening (Kildaire Farm To Seabrook) $1,700,000 Done Maynard
Road Widening (Kildaire Farm To West Chatham) $3,855,000 Easement
Negotiations Winter 2002 Start Construction Spring
2004 Finish Construction
Spring 2005 Cary
Parkway Lane Additions $400,000 Done Piney
Plains Road Widening $3,655,000 Start
Construction Fall 2003 Sidewalks Done Street
Improvements $3,375,000 Done Trinity
Road Widening, Extension N.C. 54 to Cary Towne Boulevard $2,400,000 Initial
Planning Fall 2002 Start Construction Summer 2005 Finish Construction Summer 2006 Tryon
Road Widening Kildaire Farm to Campbell Road
$5,025,000 Begin
Acquiring Right-of-way Fall 2002 Start Construction Summer 2003 Finish Construction Summer 2005 US
1/64 & Walnut Street Interchange $6,000,000 Begin
Acquiring Right-of-way Fall 2002 Start Construction Summer 2004 Finish Construction Summer 2006 US
1/64 Cary Parkway Interchange $5,000,000 Begin
Acquiring Right-of-way Fall 2002 Start Construction Summer 2004 Finish Construction Summer 2006 Walnut
Street Improvements $1,170,000 DONE * Extra-Territorial Jurisdiction (Area Beyond Town
Limits Where Town Planning And Zoning Authority Applies) Roadway Bonds Background Information - Prepared
1999 The following was compiled to educate voters for
the February 1999 bond referendum: |