|
![]() | |||||||||||||||||||||||||||||||||||||||||
|
Total Parks Bonds Approved - $10 million Fall 2002 Update Progress report on projects receiving 1999 parks
bonds that are complete or in the pipeline Project Bonds
Budgeted Status Batchelor
Branch Greenway (NC 55 to Sears Farm Road) $286,000 Began
design June 2000 Finish construction
December 2003 Ball
Fields at Davis Drive Schools & Cary High School $66,000 DONE Black
Creek Greenway (West Dynasty to NW Maynard
Road) $112,082 Began
design August 1996 Finish construction April 2003 Black
Creek Greenway (Godbold Park to Bond Park) $228,038 Began
design June 2001 Finish construction December
2003 Green
Hope Elementary Park $347,155 DONE Tennis
Center $317,423 DONE Greenway
& Open Space Acquisition $108,000 Ongoing Middle
Creek Park (Phase I) $4,667,671 DONE Land
Acquisition $2,121,234 Ongoing Speight
Branch Greenway SE Cary Parkway to Tryon Road $288,000 Began
design June 2000 Finish construction
August 2003 Tryon
Road Park Greenway $132,000 (Schedule
undetermined) Walnut
Creek Greenway (Buck Jones to Cary Towne Center) $370,000 (Schedule
Undetermined) White
Oak Park (Phase II) $435,000 DONE Parks Bonds Background Information - Prepared
1999 The following was compiled to educate voters for
the February 1999 bond referendum. |