Total Parks Bonds Approved - $10 million

Fall 2002 Update

Progress report on projects receiving 1999 parks bonds that are complete or in the pipeline

Project

Bonds Budgeted

Status

Batchelor Branch Greenway

(NC 55 to Sears Farm Road)

$286,000

Began design June 2000

Finish construction December 2003

Ball Fields at Davis Drive Schools & Cary High School

$66,000

DONE

Black Creek Greenway

(West Dynasty to NW Maynard Road)

$112,082

Began design August 1996

Finish construction April 2003

Black Creek Greenway

(Godbold Park to Bond Park)

$228,038

Began design June 2001

Finish construction December 2003

Green Hope Elementary Park

$347,155

DONE

Tennis Center

$317,423

DONE

Greenway & Open Space Acquisition

$108,000

Ongoing

Middle Creek Park (Phase I)

$4,667,671

DONE

Land Acquisition

$2,121,234

Ongoing

Speight Branch Greenway

SE Cary Parkway to Tryon Road

$288,000

Began design June 2000

Finish construction August 2003

Tryon Road Park Greenway

$132,000

(Schedule undetermined)

Walnut Creek Greenway

(Buck Jones to Cary Towne Center)

$370,000

(Schedule Undetermined)

White Oak Park (Phase II)

$435,000

DONE

 

 

Parks Bonds Background Information - Prepared 1999

The following was compiled to educate voters for the February 1999 bond referendum.


  • Parks Improvements $10M
Master Parks Plan Projects Through 2010

  • 17 Neighborhood Parks
  • 5 Community Parks
  • 1 Metro Park
  • 6 Community Centers
  • 26 Miles of Greenway