Planning and Zoning Board Report

WILLIAMS CROSSROADS OFFICE SITE

Project Number: 00-SP-221

Project Description: 

The property is located south of Dillard Drive and south of the intersection of Columbus Avenue and Dillard Drive, approximately 750’ east of the intersection of Walnut Street and Dillard Drive. The plans propose a one-story dark brown brick office building containing 21,625 square feet on 3.2 acres. The property is zoned Office and Institutional District (O&I), is in the Swift Creek, New Urban Overlay District and is inside Cary’s town limits.

Vicinity Map

 

Planning and Zoning Board Recommendation: to be completed following the Planning and Zoning Board meeting.

P&Z Comment:

 

Staff Recommendation:

Staff recommends approval of the plan.

 

Review Summary:

General Zoning Requirements

Staff Contact: Planner

Phone:  919-469-4045     Email: bbenfiel@ci.cary.nc.us

Zoning & Land Use Plan Compliance

Description: The plan complies with all zoning requirements.

 

Landscape

Description: The plan complies with all landscape requirements.

Staff Conclusion:  The Landscape Plan includes all required landscaping and incorporates tree save areas along Dillard Drive and within the eastern and southern buffer areas.

 

Building Elevations

Description: The plans propose a one-story dark brown brick office building that will utilize a stacked brick header on windows and around the top of the building. Store front framing will be clear anodized aluminum. The building also incorporates an off-white standing seam metal entrance canopy with cast in place off-white columns.

Staff Conclusion: The architectural style and exterior materials and colors will be compatible with other office buildings in the Crossroads Office Park.

 

Traffic

Staff Contact:

Dick Moore Phone:462-3937

Email: dmoore@ci.cary.nc.us

 

Description: This 21,625 sq.ft. office building will generate 238 trips per weekday. The AM peak hour is 34 trips and the afternoon peak hour trip generation is 32 trips.

Connectivity is shown on the plan to the east and west of the site for the future.

Staff Conclusion: A Traffic Impact Study is not required.

 

Roadway Design

Staff Contact:

Tammy Mitchell Phone:462-3933

Email: lmitchel@ci.cary.nc.us

 

Description: No roadway improvements are required as part of this development plan.

 

Utilities

Staff Contact:

Tammy Mitchell Phone:462-3933

Email: lmitchel@ci.cary.nc.us

 

Description: Public sanitary sewer and water mains are both located within Dillard Drive right-of-way. Service connections to these mains are proposed as part of site development.

 

Storm Water

Staff Contact:

Tom Horstman Phone:469-4347

Email: thorstma@ci.cary.nc.us

 

Description: Williams Crossroads Office Site meets all of the requirements of the stormwater section of the engineering department. Existing conditions show possible riparian buffers located on the site. Investigations by the Division of water Quality have shown that the feature was not a stream and would therefor be exempt from riparian buffer issues.

Staff Conclusion: Project meets all requirements of the Town of Cary stormwater section.

 

Appearance Commission Recommendations

1. Recommended that the roof top HVAC screen be a similar color as the HVAC screens used on the Crossroads Office Buildings (a brown color, as opposed to a light gray or white color.)

2. Recommended consideration be given to enhancing light levels at side entrances into the building and at handicap parking locations.

3. Recommended that silt fencing be added along the edge of the tree protection fencing within the western buffer.

Staff Observations:  The plan was revised to address all Appearance Commission recommendations.