TOWN OF CARY
DEVELOPMENT PLAN REPORT
Maynard Summit
Project No. 01-SP-165b

APPLICANT

OWNER

Withers & Ravenel Engineering & Surveying

Jeff Fike Builders

 

Location:

Map:

The site would be located east of SE Maynard Road, approximately 600' south of the intersection of SE Maynard Road and Sloan Drive, south and east of the Cary Masonic Lodge, and north and west of Merriwood Apartments.

 

Planning & Zoning Board Recommendation:

The Planning and Zoning Board recommended approval of the plan, with a vote of 6 yes votes to 3 no votes. The recommendation of approval included the following conditions:
  1. That the Town accept a proposed payment-in-lieu for the SE Maynard Road improvements. Staff feels that roadway widening of this magnitude would best be handled as a much larger project.
  2. That the SE Maynard Road 50' streetscape be reduced in width to 30'.
  3. That an asphalt multi-purpose court be installed in the area designated for active recreation.
  4. That an evergreen screening hedge be installed along the northern and southern sides of the passive/active recreation area.
  5. That the sewer mains and services be constructed of ductile iron pipe.

Staff Recommendation:

Staff recommends approval of the plan with the following conditions:

  1. That the Town accept a proposed payment-in-lieu for the SE Maynard Road improvements. Staff feels that roadway widening of this magnitude would best be handled as a much larger project.
  2. That the SE Maynard Road 50' streetscape be reduced in width to 30'.
  3. That an asphalt multi-purpose court with a basketball goal be installed in the area designated for active recreation.
  4. That an evergreen screening hedge be installed along the northern and southern sides of the passive/active recreation area.
  5. That the sewer mains and services be constructed of ductile iron pipe.

 

PROPOSED SCHEDULE OF MEETINGS

PLANNING & ZONING BOARD:

March 18, 2002 (Plan tabled for 30 days)
April 15, 2002 (Revised plan as Old Business)

TOWN COUNCIL:

April 25, 2002

 

PROJECT DESCRIPTION

The plan proposes 76 (formerly 85) two-story townhomes located on 7.44 acres. The site would be accessed from SE Maynard Road by a proposed drive with a divided median. This roadway would extend northward through the development to a proposed collector roadway, and a second full service drive is also proposed at the collector roadway. The collector roadway would extend westward to SE Maynard Road and eastward to the easternmost property line. A 50' streetscape is required along SE Maynard Road, but the plan proposes to reduce this streetscape to a width of 30'.

 

PARCEL INFORMATION

Parcel #

Realid #

Area

0774.17-00-4218

0774004218

7.44 acres.

 

ZONING AND LAND USE PLAN COMPLIANCE

Current Zoning: Residential-Multi-Family 12 (R-MF-12)
Overlay District:
N/A
Town Limits:
Inside
Land Use Compliance:
The Land Use Plan within the area calls for high-density residential development.

Excluding the following items, the plan complies with all zoning requirements:

  1. The plan proposes to reduce the 50' streetscape along SE Maynard Road to a width of 30'. (The original plan submittal proposed a streetscape width of 22'.) The proposed 30' streetscape would include: plantings to an opaque standard, a 6' high wrought iron fence across the property frontage, and evergreen shrubs planted along the roadway side of the fence. The actual open area between townhomes and the right-of-way line of SE Maynard Road is 40'. The townhomes would adhere to a 50' setback from the right-of-way line. Staff feels the combination of a 50' building setback, 40' of open space, opaque landscaping, and wrought iron fencing meets the intent of the 50' streetscape requirement and, therefore, staff supports the reduction in streetscape width from 50' to 30'.
  2. The plan designates an area central to the site as active recreation, but no physical improvements are proposed on the plan. Staff has recommended that the active recreation area be utilized as an asphalt multi-purpose court with an installed basketball goal.

 

WAKE COUNTY SCHOOL CAPACITY IMPACTS:

Current Enrollment

Area Schools

Building Capacity

Percent occupied

Projected Number of Additional Students

Elementary

14,909

13,127

113.6%

13

Middle

7,596

6,456

117.7%

7

High

5,629

5,100

110.4%

9

Total for all Area Schools

28,134

24,683

114%

29

Preschool

15

Current Enrollment and Building Capacity is based on the 20th day of the school year for 2001. School assignment will be determined at the time of development. A list of individual area schools can be reviewed at: School Data

Staff has received for this development a Certificate of Adequate Facilities for Schools from the Wake County School System. The Certificate indicates that adequate seating would be available at designated schools at the time of occupancy. Actual school locations would be announced.

LANDSCAPE

Excluding the request to reduce the 50' streetscape along SE Maynard Road to a width of 30', the plan complies with all other landscape requirements. Staff, however, has one remaining recommendation that has not been adequately addressed, as follows:

Staff recommends that an evergreen screen be installed along the north and south sides of the passive/active recreation area. A partial visual screen and noise barrier is needed at these locations, and an evergreen screen would satisfy this recommendation.

 

BUILDING ELEVATION

Building Height: 28'-6" (Two-story, two & three bedroom units).
Building Size:
1,200 square feet (approximate).
Building Materials & Color:
Dark brown brick foundation walls, white siding, dark gray asphalt shingled roof, and shutters and trim in corresponding colors.

 

TRAFFIC

  1. The 76 townhomes would generate 515 trips per day. The AM peak hour is 41 trips. The PM peak hour is 49 trips.
  2. No traffic study is required.

Staff Contact: Dick Moore, 462-3937, Email: dmoore@ci.cary.nc.us

 

ROADWAY DESIGN

Along this project frontage, SE Maynard Road is designated to have an ultimate 76’ back-to-back (four-lane median divided) cross section centered within a 98’ right-of-way based on the Town’s Thoroughfare Plan. The 76’ wide street section consists of a 16’ landscaped median, 12’ inside lanes and 14’ outside lanes. Currently, SE Maynard Road along this project frontage has a 65’ back-to-back (two lanes in each direction with a continuous center turn lane) cross section centered within a 90’ right-of-way. In order to comply with Town Ordinances, the developer would be required to remove existing curb and gutter and sidewalk, widen Maynard Road pavement approximately 5.5’, and then install new curb and gutter and sidewalk. The developer would also be required to dedicate approximately 4’ of right-of-way and construct or bond for "one-half" of the 16’ wide median. The developer proposes to dedicate the additional right-of-way necessary to meet current Thoroughfare Plan requirements, but is requesting to make a payment-in-lieu of Maynard Road improvements. Due to the parcels limited frontage, the minimal amount of additional pavement that would be provided and the requirement for a center median, staff supports the developers request to make a payment-in-lieu of Maynard Road improvements. Staff feels that a widening of this nature would best be handled as a much larger project.

The Town’s Thoroughfare Plan calls for a new east-west collector street to be constructed from SE Maynard to the proposed Trinity Road Extension (from E. Chatham Street to Cary Towne Boulevard). This collector street is shown on the Town’s Thoroughfare Plan to align with Sloan Drive. The Maynard Office Center site plan (just north of proposed Maynard Summit) was approved by the Town in 1996 and the proposed collector street was not required as part of that plan approval. In researching the Maynard Office project file, no mention of the proposed collector could be found and it is staff’s opinion that this item was overlooked during the review and approval of the Maynard Office site plan.

The developer of proposed Maynard Summit, in response to emergency access concerns, as well as trying to work with staff to meet the intent of the Town’s Thoroughfare Plan, has proposed a reduced collector street cross section within the 60’ strip of land along the parcels northern boundary between Maynard Office Center and the Family Funds development, in order to provide a second point of access to the development. The reduced cross section is necessary due to grading constraints because of existing developments on either side. Staff supports the design as shown.

Staff Contact: Tammy Spivey, 462-3933, Email: tspivey@ci.cary.nc.us

 

UTILITIES

Water and Sewer: The proposed development will connect to Cary public water and sewer systems. The plan complies with TOC utility standards and policies, however, staff recommends that the sewer mains and services be constructed of ductile iron pipe rather than PVC pipe.

The sewer system would be located beneath private drives and parking areas where Cary has no authority or control over driveway and utility service repair, therefore, staff has recommended that the public sewer system be constructed of a more durable material, ductile iron pipe.

Staff Contact: Shuyan Tian, 469-4381, Email: stian@ci.cary.nc.us

 

STORM WATER

The project has addressed all the stormwater requirements of the Town of Cary.

Staff Contact: Tom Horstman, 469-4347, Email: thorstma@ci.cary.nc.us

 

PROPERTY OWNER NOTIFICATION AND CONCERNS

The adjoining property owners were notified of the proposed development during staff's first review of the plan. Staff has received no inquiries from adjoining property owners regarding this development plan.