- Swift Creek Parallel Force Main
- Green Level Church Road Force Main (O'Kelly Chapel Road to Kit Creek PS)
- Town Hall Pump Station Elimination
- Western Wake Regional Wastewater Management Facilities
- Kit Creek Pump Station Phase 2 Expansion
- Holly Brook Pump Station and Force Main
- Wastewater Pump Station Parallel Force Mains
- Paramount Pump Station Elimination
- Dutchman's Branch Pump Station, Force Main, and Interceptor
- Wastewater Collection System Study and Master Plan
- 30" Force Main and 16" Reclaimed Water Line along Green Level Church Road (McCrimmon Parkway to Carpenter Fire Station Road)
- Green Level Interceptor and Pump Station Elimination
Green Level Church Road Force Main (O'Kelly Chapel Road to Kit Creek PS)
Overview: This project consists of 4,275 feet of 24-inch force main connection from the existing 24-inch force main at the intersection of O'Kelly Chapel Road and Green Level Church Road north to the Kit Creek Pump Station. Completion of this project will allow the Kit Creek Pump Station to pump south to the West Cary Pump Station and finally to the Western Wake Plant instead of curently pumping to Durham County.
Schedule: Construction will begin in spring 2012.
Contact: Jamie Bissonnette, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-2760
jamie.bissonnette@townofcary.org
Town Hall Pump Station Elimination
Overview: This project provides for the construction gravity sewer line between the Town Hall Drive pump station and a new downstream gravity sewer provided by recent development in Morrisville. Construction of this line conveying to the new gravity sewer line will allow for the elimination of the Town Hall Drive pump station. The elimination of this pump station allows the Town to utilize newly developed gravity service in this area and eliminates the possibility of potential pump station failure.
Schedule: Construction will begin in summer 2012.
Contact:
Jamie Bissonnette, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-2760
jamie.bissonnette@townofcary.org
Western Wake Regional Wastewater Management Facilities
Overview: This item includes several regional wastewater projects to meet future service area needs and regulatory requirements for the Towns of Apex, Cary, and Morrisville. Detailed project information can be viewed here: http://www.westernwakepartners.com.
Schedule: These projects are currently being permitted. Construction may begin in spring 2012.
Contact:
Alexandra Jones, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 462-3836
alexandra.jones@townofcary.org
Bachelor Branch Interceptor and Pump Station Elimination Project
Overview: Phase 1 of this project provides approximately 4,300 linear feet of 36-inch diameter gravity sewer line along Bachelor Branch from the intersection of Green Level West Road to the West Cary Pump Station, located at 3905 Green Level West Road. Phase 1 of the Bachelor Branch Interceptor provides gravity sewer service to the surrounding area, and conveys sewage from the White Oak Interceptor to the West Cary Pump Station.
Phase 2 of this project provides for 7,300 linear feet of 30-inch and 16-inch diameter gravity sewer line along Bachelor Branch from the existing Fieldstone pump station to the intersection of Green Level West Road, where it will intersect with Phase 1 of this project. Once completed, the Bachelor Branch Interceptor will provide gravity sewer service to the surrounding area. Also, the existing Fieldstone Pump Station, which would require expansion and improvement to remain in service, will be removed from service, eliminating any potential failure of the pump station while reducing associated maintenance costs for sewer service in this area.
Phase 2 also provides for 1,200 lf of 12-inch diameter gravity sewer line that will reach to the Thomas E. Brooks Park and USA Baseball National Training Center. Once completed, this line will provide gravity sewer service to the park and will allow the existing Thomas Brooks Park Pump Station to be removed from service, eliminating any potential failure of the pump station while reducing associated maintenance costs for sewer service in this area
Schedule: Phase 1 of this project is complete. Phase 2 of this project is currently under construction, with completion scheduled for early 2010.
Contact: The Town of Cary welcomes public comment. Feel free to write, call or e-mail:
Jarrod A. Buchanan, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-2760
jarrod.buchanan@townofcary.org
Windsor Oaks Water and Sewer Extension Project
Overview: The Windsor Oaks Project consists of providing water and sewer service to the Windsor Oaks community, along Kingsford Drive, Bexhill Drive, East Bridgeford Drive, West Bridgeford Drive, Astor Court, and Woodington Court. The Windsor Oaks community petitioned the Town of Cary to receive water and sewer service. The project was subsequently approved by Council in January 2004. The residents of the Windsor Oaks community currently utilize a community well and sewer systems, operated by AQUA. This project, when completed, will provide approximately 8,700 feet of sewer mains, 6,000 feet of water mains, and water and sewer services to 90 Town of Cary residents.
Schedule: This project is currently under construction, with completion scheduled for early 2010.
Contact: The Town of Cary welcomes public comment. Feel free to write, call or e-mail:
Jarrod A. Buchanan, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-2760
jarrod.buchanan@townofcary.org
Kit Creek Pump Station Phase 2 Expansion
Overview: This project will expand the existing Kit Creek Pump Station from its current 8.3 MGD capacity to 12 MGD. This expansion will allow the Town of Cary to provide sufficient sewer capacity serving the rapidly developing NW areas of Cary.
Schedule: This project has being permitted. Construction can begin at any time. Staff is monitoring flow data to determine construction schedule.
Contact:
Shuyan Tian, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 469-4381
shuyan.tian@townofcary.org
Holly Brook Pump Station and Force Main
Overview: This project includes the construction of a 565 gpm pump station, 3,300 feet 12” gravity sewer, and 7,750 feet forcemain, as well as the abandonment of an existing pump station. Once the new pump station is completed, it will provide sanitary sewer service to the Town of Cary’s utility service area west of Kildaire Farm Road and south of Ten Ten Road.
Schedule: This project is currently 'On Hold'
Contact:
Shuyan Tian, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 469-4381
shuyan.tian@townofcary.org
Wastewater Pump Station Parallel Force Mains
Overview: This project includes the design and construction of new force mains to provide redundancy to existing critical force mains. Parallel force mains will be constructed for the Walnut Creek Pump Station, Crossroads Pump Station, Jones Franklin Pump Station, and Aviation Parkway Pump Station. Additional pump stations may be added as the project progresses. These force mains will make it possible to take force mains down for preventative maintenance and cleaning, as well as provide additional operational flexibility to the system.
Schedule: This project is currently under design. Construction for some of the force mains may begin in Winter 2012.
Contact: Betsy Drake, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 481-5093
betsy.drake@townofcary.org
Wastewater Collection System Study and Master Plan
Overview: The Town of Cary completed its most recent wastewater collection system master plan in 2003. Since that time, there have been a number of changes to the wastewater system, such as taking ownership of the Town of Morrisville utilities and the detailed planning for the new Western Wake Regional Wastewater Treatment Facility. An updated master plan is necessary to address these and other changes in the collection system. The information in the master plan will be used to plan and prioritize future collection system improvements.
Schedule: This project is currently underway. The new master plan is estimated to be complete in Spring 2012.
Contact:
Betsy Drake, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 481-5093
betsy.drake@townofcary.org
Paramount Pump Station Elimination
Overview: This project provides for the elimination of the Paramount Pump Station through the installation of approximately 3,000 feet of 12-inch gravity sanitary sewer. Abandoning the existing pump station will avoid the need for future pump station and force main maintenance and upgrades. In addition, the proposed gravity sewer will help alleviate wastewater capacity issues in the Perimeter Park basin.
Schedule: This project is currently on 'Hold'.
Contact: David Hallgren, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 481-5095
dave.hallgren@townofcary.org
Dutchman's Branch Pump Station, Force Main, and Interceptor
Overview
The Dutchman’s Branch Regional Pump Station, Force Main, and Interceptor Project is a result of the growth in the southern part of the Town and will increase the Town’s serviceable area. The project will also eliminate two smaller pump station sites whereby also eliminating the potential for those pump stations to fail and the maintenance costs associated with them.
Description – 6,000 feet of 20-inch gravity sanitary sewer interceptor will be constructed along Dutchman’s Branch from east of Kildaire Farm Road to Holly Springs Road. At the eastern terminus of the interceptor a sewer pump station will be built. 4,000 feet of 12-inch sanitary sewer force main will be extended to the existing Camp Branch interceptor. Following the activation of these facilities, the Glenridge pump station and the Powell Tract II pump station will be eliminated.
Status – Project is on 'Hold'
Contact
Robert Hirt, P.E.
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 481-5099
robert.hirt@townofcary.org
Overview: This project consists of 2,000 FT of 30-inch force main and 2,600 Reclaimed Water line along Green Level Church Road from McCrimmon Parkway to Carpenter Fire Station Road. The widening of Green Level Church Road within these limits is scheduled to be completed by the end of 2011. However, the road widening project does not include a section sidewalk and the greenway trail along Green Level Church Road.
The sidewalk and greenway trail along Green Level Church are scheduled to be built upon completion of the 30" force main along the northbound lanes of Green Level Church Road and a 16" reclaimed water line along the southbound lanes of Green Level Church Road.
Schedule: Construction will begin in spring 2012.
Contact:
Jamie Bissonnette, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 380-2760
jamie.bissonnette@townofcary.org
Green Level Interceptor and Pump Station Elimination Project
Overview: Phase 1 of this project provides approximately 4,430 linear feet of 48-inch diameter gravity sewer line and 40 linear feet of 8-inch diameter gravity sewer line along an unnamed tributary of White Oak Creek, from the West Cary Pump Station located at 3905 Green Level West Road to the Woodlands Pump Station, located at 7748 Mill Road. Phase 1 of the Green Level Interceptor shall provide gravity sewer service to the surrounding area, and convey sewage to the West Cary Pump Station. Also, the Woodlands Pump Station will be removed from service, eliminating any potential failure of the pump station while reducing associated maintenance costs for sewer service in this area.
Phase 2 of this project provides for 1,250 linear feet of 48-inch diameter gravity sewer and 700 linear feet of 12-inch diameter gravity sewer line along from the existing gravity sewer line located at the end of Starcross Court to Hendrix Road and then to the Palaver Pump Station. Phase 2 of the Green Level Interceptor shall provide gravity sewer service to the surrounding area. Also, the Palaver Pump Station will be removed from service, eliminating any potential failure of the pump station while reducing associated maintenance costs for sewer service in this area.
Phase 3 of this project provides for 4,350 linear feet of 48-inch diameter gravity sewer from the end of Phase 2, continuing along the same unnamed tributary and will tie into an existing force main approximately 1,200-feet north of the intersection of Green Level Church Road and Green Hope School Road. Phase 3 of the Green Level Interceptor shall provide gravity sewer service to the surrounding area and allow waste water to flow by gravity from the existing force main down to the West Cary Pump Station.
Schedule: This project is currently under design. Construction is anticipated to begin the first quarter of 2013.
Contact: The Town of Cary welcomes public comment. Feel free to write, call or e-mail:
Jarrod A. Buchanan, PE
Town of Cary Engineering Department
P.O. Box 8005
Cary, NC 27512-8005
(919) 469-4335
jarrod.buchanan@townofcary.org