2010 NCDOT Resurfacing Projects

Overview

The North Carolina Department of Transportation (NCDOT) will be resurfacing various state maintained roadways within the Town of Cary.

Project Schedule

NCDOT will be performing work on the following:

ROAD RESURFACING LIMITS BEGIN CONSTRUCTION COMPLETE CONSTRUCTION NCDOT CONTACT
Walnut Street
US-1/64 Ramp to South of Dillard Drive SPRING 2010 FALL 2010 Resident Engineer
840-0914
Campbell Road
Tryon Rd. to Holly Springs Rd.  SPRING 2010  FALL 2010 Resident Engineer
840-0914
N.W. Maynard Road  Bridge over Railroad to High House Rd.
SUMMER 2010 FALL 2010 Resident Engineer
840-0914
Kildaire Farm Road Walnut Street to Palace Green SUMMER 2010 FALL 2010
Resident Engineer
840-0914
US-64 Highway  NC 55 to US-1 Interchange SPRING 2010 FALL 2010 Resident Engineer
733-9499
Tryon Road US-1 Interchange to Cresent Green SPRING 2010
FALL 2010 Resident Engineer
733-9499
East Chatham Street East Durham Road
Split to NE Maynard
Road
SUMMER 2010 FALL 2010 Resident
Engineer
733-9499
Holly Springs Road Curve Improvements
and 800 foot of
Resurfacing at Southbriar Drive (LocationApproximately 300 ft South of Penny Road)
SUMMER 2010 FALL 2010 Resident Engineer
733-9499


Details

The project will require periodic lane closures and traffic shifts on the roadways through the duration of construction. Work will be performed Monday through Sunday with every effort to minimize impact to the traveling public. Work may also be performed on the evenings and weekends.

Work will consist of milling, traffic signal loop replacement, utility adjustments, paving and new pavement markings.

Contact

For additional information regarding work on the above roadways, please contact the appropriate NCDOT Resident Engineers Office.