2011 NCDOT Resurfacing Projects
Overview
The North Carolina Department of Transportation (NCDOT) will be resurfacing various state maintained roadways within or adjacent to the Town of Cary.
Project Schedule
NCDOT will be performing work on the following: Note: "SR" means "State Route which is NCDOT maintained'.
|
ROAD |
RESURFACING LIMITS |
BEGIN CONSTRUCTION |
COMPLETE CONSTRUCTION |
NCDOT CONTACT |
|
SR 1152 Holly Springs Road |
From Ten-Ten Road to NC 55-Main Street. This section excludes the new pavement project at Sunset Lake Road. |
Spring 2011 |
Fall 2011 |
Resident Engineer, Jeffery Allen, P.E. (919) 733-9499 |
|
SR1390 Optimist Farm Road |
From West Lake Road to Lake Wheeler Road Length of improvements is 2.3 miles. |
Spring 2011 |
Fall 2011 |
Resident Engineer, Jeffery Allen, P.E. (919) 733-9499 |
|
SR1009 |
From Traffic Signal at Crescent Green to New Waverly Place. |
Spring 2011 |
Fall 2011 |
Resident Engineer, Jeffery Allen, P.E. (919) 733-9499 |
|
SR1152 Holly Springs Road |
From Pavement Joint South of Curve Widening at South Brier Drive to Pavement Joint North of South Brier Drive. |
Spring 2011 |
Fall 2011 |
Resident Engineer, Jeffery Allen, P.E. (919) 733-9499 |
Details
The project will require periodic lane closures and traffic shifts on the roadways through the duration of construction. Work will be performed Monday through Sunday with every effort to minimize impact to the traveling public. Work may also be performed on the evenings and weekends.
Work will consist of milling, patching, shoulder reconstruction on various routes, traffic signal loop replacement, utility adjustments, paving and new pavement markings.
Contact
For additional information regarding work on the above roadways, please contact the appropriate NCDOT Resident Engineers Office.