The Town of Cary plans to pave and extend the existing gravel roadway known as Old Maynard Road approximately 0.65 miles from Redwood Park Drive Northwest to the Little Drive and Louis Stephens Drive Intersection in Research Triangle Park. (See map).

Schedule (Tentative)

Complete Design Winter 2012
Complete right-of-way easement negotiations Summer 2012
Begin Construction Spring 2013
Complete Construction/Open to Traffic Winter 2013


Details

  • Project provides a 2-lane paved roadway from Redwood Park Drive in Morrisville to Little Drive in Research Triangle Park.
  • When the project is completed, this roadway will be maintained by the North Carolina Department of Transportation.
  • The existing roadway known as Old Maynard Road will be renamed Louis Stephens Drive when paved and extended to Research Triangle Park.

 

Background

The Town has budgeted a total of $1,866,500 to construct this project. The project will ease congestion in this section of Cary by providing an additional route to Research Triangle Park.

Contact

The Town of Cary welcomes public comment on the project. To respond by mail, phone or e-mail contact: