NEWS RELEASE
|
FOR IMMEDIATE RELEASE |
|
CARY
MANAGER SAYS
SWIFT CREEK ASSESSMENT INSUFFICIENT
Town
to Hire Independent Analyst
CARY, NC – The Town of Cary will hire an
independent third party to conduct a second assessment of recent events at the
Town of Cary’s Swift Creek Regional Pump Station since findings issued today
by the project’s engineering firm, Black & Veatch, fell short of Town
Manager Bill Coleman’s expectations. Black
& Veatch’s assessment was to have detailed the events leading up to the
dislodgement of a pump station pipe on June 23, the Town and private
contractors’ responses to the emergency, and recommendations on how to better
handle similar situations should they arise in the future.
After reviewing the document, Coleman felt that while it was a good
start, several issues would benefit from further analysis from a different
perspective.
“The assessment was to
provide the Town with an honest, accurate, detailed, and complete evaluation of
the event, and it did not,” said Coleman.
Among Coleman’s specific
concerns were insufficient specificity as to the cause of the pipe becoming
dislodged and a lack of context for several actions and events.
He also felt that the recommendations were relatively generic.
“The bottom line is that
we don’t have confidence that the assessment provided a full picture of what
happened,” said Coleman.
While Coleman could not
offer an exact timetable for the second analysis, he stressed that the issue
remains one of his top priorities and would be resolved as soon as possible,
likely within the next 60 days. He
added that despite the assessment having fallen short of expectations, Black
& Veatch would continue on the project team to expand the pump station.
In August 2005, the Town of
As part of the expansion, the contractor excavated a
large area near the existing pump station. Heavy
rains from severe thunderstorms on June 23 filled the hole, a soil embankment
collapsed, and a pipe critical to the station’s operations was dislodged.
In order to repair the pipe, workers had to shut down the pump station,
after which the sewage normally moving through the station began going into
Swift Creek.
Initial attempts to reposition the pipe failed, and on
June 24, crews were able to implement an extensive, around-the-clock pump and
haul operation to help keep sewage from overflowing into the creek.
The pump and haul operation, which included up to 20 6,500-gallon tanker
trucks, continued for more than 100 hours until June 28 when workers were able
to activate a temporary, onsite bypass pumping operation that completely
replaced the work normally done by the disabled Swift Creek station.
During the five days between the pump station’s
idling and the activation of the onsite bypass, Cary estimated that as much as
7.9-million gallons of untreated waste—or about 32% of the station’s average
flow for a 5-day period—probably made its way into Swift Creek.
No fish kill was observed, but the situation closed several downstream
lakes as well as
Each year, the Town of
###
|
PRIMARY CONTACTS: |
Bill Coleman, Town Manager, (919) 469-4002 April R. Little, Deputy Public Information Officer, (919) 481-5091 Susan Moran, Public Information Officer, (919) 393-4383 (pager) |
